Priorities for Road System Projects
El Dorado Hills Citizens Alliance
| Pink -- Highest priorities for El Dorado Hills |
| Yellow -- Medium priorities for El Dorado Hills |
| Green -- Lesser priorities for El Dorado Hills |
| Gray -- EDH projects already completed |
| White -- Non-EDH projects, not prioritized |
| Project # | Project Name / Description |
||||
| not listed | US 50 westbound auxiliary lane, El Dorado Hills Blvd to county line | ||||
| not listed | US 50 widening, one additional through traffic lane in each direction Bass Lake Road to county line | ||||
| not listed | Green Valley Road: Widen to four lanes from Francisco Drive to Cameron Park Drive | ||||
| not listed | North/south arterial on west side of EDH Business Park General
Plan Policy TC-1u: "The County shall amend the circulation
diagram to include a new arterial roadway from the west side of the El
Dorado Hills Business Park to U.S. 50." General Plan Measure TC-V(1): "Work with the Sacramento Area Council of Governments (SACOG), Sacramento County and the City of Folsom to identify potential alignments for a new arterial roadway from the west side of El Dorado Hills Business Park to U.S. Highway 50. [Policy TC-1u]" | ||||
| not listed | Additional arterials:
The overall El Dorado Hills road network needs additional arterials to
form a well-interconnected road network and to relieve traffic on
arterials which are approaching overload during peak hours. Green
Valley Road is now in that class. | ||||
| not listed | Improve rural roads and intersections to at least suburban standards for purposes of traffic safety. There are several examples of such roads north of Green Valley Road due mainly to increased traffic in areas with limited sight distance, limited roadway width, and in some locations absence of shoulders. | ||||
| not listed | Transit service to EDH Business Park General Plan Policy TC-1v: "The
County shall consider modification of the circulation diagram to
include a frequent transit service operating on exclusive right-of-way
to the El Dorado Hills Business Park from residential communities in El
Dorado County and from the City of Folsom." General Plan Measure TC-V(3): "Identify right-of-way needed for potential establishment of a frequent transit service operating on exclusive right-of-way to the El Dorado Hills Business Park from residential communities in El Dorado County and from the City of Folsom. Consider modification of the Circulation Map to include the identified right-of-way. [Policy TC-1v]" | ||||
| (related) | Not a CIP project, but essential to prioritization of CIP projects -- General Plan Measure TC-V(2): The
County shall implement a mechanism for all new discretionary and
ministerial development (which includes approved development that has
not yet been built) that would access Latrobe Road or White Rock Road.
This mechanism shall be designed to ensure
that the 2025 p.m. peak hour volumes on El Dorado Hills Boulevard,
Latrobe Road, and White Rock Road do not exceed the minimum acceptable
LOS thresholds defined in Policies TC-Xa through TC-Xe with the
circulation diagram improvements assumed in place. As such, the measure
should consider a variety of methods that control or limit traffic. The
County shall monitor peak hour traffic volumes and LOS beyond 2025 and,
if necessary, shall implement growth control mechanisms in any part of
the county where the LOS thresholds defined in the General Plan
policies listed above cannot be maintained. General Plan Policy TC-Xd defines the minimum acceptable LOS threshold to be LOS E in community regions. The EDH Citizens Alliance considers this to be an inappropriately low threshold. We have not formally adopted a recommendation for a different threshold, but it is reasonable to suggest that those whose interests we advocate for would accept a standard of LOS B. Some may be willing to accept LOS C, but we believe it is very unlikely that many would accept LOS D or worse as a reasonable standard. | ||||
| Project # | |||||
| 53110 | U.S. 50 HOV Lanes (Phase 1) - El Dorado Hills to Bass Lake Grade (HOV lanes on US 50 are needed much less than mixed-flow lanes.) |
October 2008 | August 2008 | $40,469,950 | Map |
| 53113 | U.S. 50 HOV Lanes (Phase 2) - Bass Lake Grade to Ponderosa Road | November 2008 | October 2010 | $2,612,063 | Map |
| 53116 | U.S. 50 HOV Lanes (Phase 3) - Ponderosa Road to Greenstone Road | November 2008 | April 2013 | $52,848,221 | Map |
| 53120 | U.S. 50 Mainline Widening at El Dorado Hills | September 2008 | July 2012 | $2,507,972 | Map |
| 66106 | Green Valley Road/Silver Springs Parkway Intersection Signalization | October 2008 | September 2008 | $1,691,012 | Map |
| 66107 | Silver Springs Pkwy to Green Valley Rd (north segment) | October 2008 | September 2008 | $8,167,939 | Map |
| 66108 | Silver Springs Pkwy to Bass Lake Rd (south segment) | October 2008 | April 2009 | $6,283,606 | Map |
| 66109 | Bass Lake Road Full Improvements - Phase 1A | November 2008 | June 2009 | $11,623,083 | Map |
| 66114 | Green Valley Road/Deer Valley Road West Intersection Improvements | October 2008 | September 2008 | $1,488,468 | Map |
| 71317 | U.S. 50/Missouri Flat Road Interchange Improvements - Phase 1A | July 2007 | September 2006 | $34,919,530 | Map |
| 71319 | U.S. 50/Camino Area Parallel Capacity/Safety Study | July 2007 | June 2015 | $4,300,827 | Map |
| 71323 | U.S. 50/El Dorado Hills Boulevard Interchange Improvements | October 2008 | May 2013 | $24,464,427 | Map |
| 71324 | Saratoga Way Extension - Phase 1 | October 2008 | NA | $1,242,286 | Map |
| 71328 | U.S. 50/Silva Valley Parkway Interchange - Phase 2 | September 2008 | June 2009 | $52,074,209 | Map |
| 71330 | U.S. 50/Bass Lake Road Interchange Improvements - Phase 1 | September 2008 | December 2012 | $20,829,113 | Map |
| 71332 | U.S. 50/Cambridge Road Interchange Improvements - Phase 1 | October 2008 | NA | $10,644,833 | Map |
| 71333 | U.S. 50/Ponderosa Rd/So. Shingle Rd Interchange Improvements | June 2008 | September 2014 | $1,105,733 | Map |
| 71335 | U.S. 50/Silva Valley Parkway Interchange - Phase 1 | November 2008 | May 2009 | $12,212,225 | Map |
| 71336 | U.S. 50/Missouri Flat Road Interchange Improvements - Phase 1B | July 2007 | April 2009 | $37,576,226 | Map |
| 71338 | U.S. 50/Ponderosa Rd Interchange - Durock Rd Realignment | March 2008 | April 2013 | $7,041,280 | Map |
| 71339 | U.S. 50/Ponderosa Rd Interchange - N. Shingle Rd Realignment | March 2008 | July 2012 | $8,518,712 | Map |
| 71340 | U.S. 50/El Dorado Hills Blvd Interchange - Pedestrian Overcrossing | October 2008 | March 2013 | $5,729,616 | Map |
| 71347 | U.S. 50/El Dorado Road Interchange Improvements - Phase 1 | March 2008 | October 2012 | $3,539,768 | Map |
| 71375 | Headington Road Extension - Missouri Flat Road to El Dorado Road | January 2008 | March 2009 | $732,803 | Map |
| 72304 | Northside School Class 1 Bike Paths | January 2009 | April 2010 | $1,336,726 | Map |
| 72332 | El Dorado Hills Boulevard/Francisco Drive Intersection Alignment | September 2008 | May 2012 | $5,899,022 | Map |
| 72334 | Diamond Springs Parkway - Phase 1 | March 2008 | October 2009 | $13,655,783 | Map |
| 72334a | Missouri Flat Rd - Pleasant Valley Rd Connector | December 2007 | NA | $0 | Map |
| 72343 | Cameron Park Drive Operational Improvements | June 2007 | NA | $711,743 | Map |
| 72361 | U.S. 50/Cameron Park Drive Interchange Improvements - Phase 1 | March 2008 | June 2013 | $5,144,858 | Map |
| 72364 | Cameron Park Drive/Country Club Drive/Palmer Drive Intersection Improvements | September 2008 | September 2007 | $2,445,082 | Map |
| 72366 | Cameron Park Drive/La Canada Drive Intersection Improvements | September 2007 | May 2008 | $2,202,517 | Map |
| 72367 | Cameron Park Widening - 3-Lane Divided to Modified 4-Lane from Durock Road to Coach | March 2008 | July 2009 | $420,350 | Map |
| 72401 | White Rock Road Realignment - Manchester Drive to Latrobe Road (project already complete) |
September 2008 | September 2007 | $7,557,298 | Map |
| 72403 | Latrobe Road Widening (2 to 4 lane) - Suncast Lane to Golden Foothill Parkway (South) | September 2008 | March 2007 | $11,510,404 | Map |
| 73113 | Green Valley Road Sidewalk from Pleasant Grove School to Bass Lake Road (project already complete) |
August 2008 | April 2008 | $664,231 | Map |
| 73150 | Cameron Park Drive/Green Valley Road Intersection Improvements | July 2007 | July 2012 | $870,975 | Map |
| 73307 | Mother Lode Drive/Pleasant Valley Road Intersection Improvements | June 2007 | June 2014 | $7,782,114 | Map |
| 73312 | Green Valley Road/Silva Valley Parkway Intersection Signalization (project already complete) |
June 2007 | February 2006 | $2,737,183 | Map |
| 73320 | Pleasant Valley Road (SR 49)/Patterson Drive Intersection Signalization | June 2007 | January 2010 | $6,557,966 | Map |
| 73354 | Durock Road/Business Drive Intersection Signalization | October 2008 | May 2008 | $4,203,440 | Map |
| 73357 | Marshall Grade Realignment | August 2008 | May 2008 | $682,876 | Map |
| 73358 | Pleasant Valley Road at Oak Hill Road Intersection Improvements | June 2007 | NA | $1,000,000 | Map |
| 73359 | Latrobe Road North of Ryan Ranch Road (Milepost 7.0 - 7.35) | October 2008 | February 2009 | $1,432,578 | Map |
| 77109 | Green Valley Road at Tennessee Creek - Bridge Replacement | February 2009 | December 2009 | $7,582,185 | Map |
| 77114 | Green Valley Road at Weber Creek - Bridge Replacement | July 2007 | April 2011 | $10,459,696 | Map |
| 77115 | Sly Park Road at Clear Creek Crossing - Bridge Rehabilitation | September 2007 | July 2010 | $4,045,452 | Map |
| 77116 | Bucks Bar Road at the North Fork Cosumnes River - Bridge Rehabilitation | June 2007 | February 2011 | $4,417,194 | Map |
| 77117 | Rubicon Trail at Ellis Creek - Bridge Replacement | February 2009 | May 2010 | $771,358 | Map |
| 77118 | Wentworth Springs Road at Gerle Creek - Bridge Replacement | February 2009 | May 2010 | $1,146,278 | Map |
| 95-73120 | Apache Avenue/US 50 Intersection Signalization | December 2007 | June 2011 | $8,690,209 | Map |
| 95147 | Angora Creek SEZ Restoration Project | December 2008 | June 2003 | $5,132,446 | Map |
| 95148 | Sawmill Bike Path | February 2009 | June 2007 | $5,960,397 | Map |
| 95153 | Boulder Mountain Erosion Control Project | January 2009 | June 2011 | $2,755,532 | Map |
| 95155 | Montgomery Estates Erosion Control Project | September 2008 | April 2010 | $3,775,999 | Map |
| 95157 | CSA #5 Erosion Control Project | July 2007 | May 2011 | $1,798,000 | Map |
| 95159 | Christmas Valley 2 Erosion Control Project | September 2008 | June 2009 | $2,555,430 | Map |
| 95160 | Angora 3 Erosion Control Project | December 2008 | November 2007 | $2,233,403 | Map |
| 95161 | Angora Creek Fisheries Enhancement Project | September 2008 | November 2008 | $1,704,389 | Map |
| 95163 | Lake Tahoe Boulevard Erosion Control Project | September 2008 | June 2009 | $1,743,610 | Map |
| 95164 | Angora 3B Erosion Control Project | September 2008 | November 2007 | $1,125,475 | Map |
| 95165 | Sawmill 2 Bike Path & Erosion Control Project | September 2008 | May 2009 | $5,578,762 | Map |
| 95166 | North Upper Truckee SEZ Restoration Project | September 2008 | June 2010 | $1,066,260 | Map |
| 95168 | South Upper Truckee I Erosion Control Project | August 2007 | June 2010 | $6,625,649 | Map |
| 95169 | Echo View 2 Erosion Control Project | January 2009 | May 2010 | $1,052,028 | Map |
| 95175 | Lake Tahoe Boulevard SEZ Project | September 2008 | June 2009 | $7,115,024 | Map |
| 95176 | Golden Bear Erosion Control Project | July 2007 | June 2012 | $3,034,271 | Map |
| 95178 | Rubicon 5 Erosion Control Project | September 2008 | May 2010 | $1,569,102 | Map |
| 95180 | Glenridge Erosion Control Project | July 2007 | June 2012 | $2,750,000 | Map |
| 95183 | Apalachee Phase 3B Erosion Control Project | September 2008 | January 2008 | $2,007,234 | Map |
| 95186 | Lake Tahoe Boulevard Bike Trail Project | September 2008 | June 2009 | $5,783,402 | Map |
| 95187 | Cold Creek Fisheries Enhancement Project | January 2009 | June 2009 | $382,710 | Map |
| 95189.1 | Thunderbird 1 Erosion Control Project | July 2007 | June 2012 | $0 | Map |
| 951MC | Meyers Corridor Operational Improvements | July 2007 | June 2011 | $0 | Map |
| 95708 | Highway 89 Class 1 Trail | July 2007 | June 2011 | $4,670,000 | Map |
| 95708.3 | Christmas Valley 2C Erosion Control Project | July 2007 | June 2011 | $360,000 | Map |
| GP124 | Country Club Drive Extension - Bass Lake Road to Silver Dove Road | November 2008 | May 2009 | $1,457,310 | Map |
| GP125 | Country Club Drive Ext. - Silver Dove Rd to west Bass Lake Hills SP Boundary | November 2008 | June 2013 | $7,019,000 | Map |
| GP126 | Country Club Drive Realignment - Bass Lake Road to east Bass Lake Hills Specific Plan Boundary | November 2008 | June 2011 | $6,745,300 | Map |
| GP135 | White Rock Road Widening (2 to 4 lanes) - Latrobe Road to US 50/Silva Valley Parkway Interchange | November 2008 | February 2012 | $1,850,000 | Map |
| GP137 | White Rock Road Widening (2 to 4 lanes) - Manchester Drive to Sacramento County Line | November 2008 | August 2011 | $12,835,400 | Map |
| GP163 | Missouri Flat Rd Two-Way Left Turn Lane - El Dorado Rd to Headington Rd | July 2007 | March 2012 | $1,482,000 | Map |
| GP165 | Missouri Flat Road Widening, Headington Road to Prospector's Plaza | January 2008 | March 2011 | $1,624,000 | Map |
| GP171 | Durock Road Widening - Robin Lane to South Shingle Road | August 2007 | June 2013 | $940,000 | Map |
| GP184 | State Route 49 & State Route 193 Intersection Signalization | July 2007 | NA | $0 | Map |